TIME RISK ANALYSIS OF IMPLEMENTATION SELF-MANAGED COMMUNITY PROJECT IN KALIANYAR - BANGIL VILLAGE

Authors

  • Luqman Cahyono Politeknik Perkapalan Negeri Surabaya
  • Mirna Apriani Politeknik Perkapalan Negeri Surabaya
  • Anggara Trisna Nugraha Politeknik Perkapalan Negeri Surabaya
  • Agung Prasetyo Utomo Politeknik Perkapalan Negeri Surabaya

DOI:

https://doi.org/10.21009/jpensil.v11i2.25078

Keywords:

Self-Managed, Project, Time Risk

Abstract

Self-managed project through of KOTAKU (Kota Tanpa Kumuh) program managed by Lembaga Keswadayaan Masyarakat Abdi Karya Amanah Kalianyar - Bangil Village received around 1 billion funds from Direktorat Jenderal Cipta Karya Kementrian Pekerjaan Umum Dan Perumahan Rakyat. The implementation of self-managed projects is carried out entirely by the community with less knowledge regarding building construction. The research objective is to identify and analyze time risks in implementing community self-managed projects. The data analysis method used is literature study, observation, average analysis, risk analysis and risk matrix preparation. The results of the analysis show that there are 20 risk variables with the highest ranking being low labor productivity where the measurement scale is likely to occur >60–80% and the risk impact on time is >7-30 days from the duration of the project, then the risk response decision "Avoidance" risk must be avoided.

References

Dewi A I,and Nurcahyo C B. (2013) ‘Analisa Risiko pada Proyek Pembangunan Underpass di Simpang Dewa Ruci Kuta Bali’, JURNAL TEKNIK POMITS, Vol. 2, No. 2, (2013) ISSN: 2337-3539
Flanagan, R dan Norman, G. 1993. Risk Management and Construction. Oxford: Blackwell Publishing. 224 p
Hanafi, Mamduh M. 2009. Manajemen Resiko, Edisi Kedua. Yogyakarta: Unit Penerbit dan Percetakan, Sekolah Tinggi Ilmu Manajemen, YKPN.
Kurniawan, Bagus Yuntar. 2011 “Analisa Risiko Konstruksi Pada Proyek Pembangunan Apartemen Petra Square Surabaya” Jurnal Teknik Sipil Institut Teknologi Sepuluh Nopember Surabaya.
Peraturan Presiden Nomor 54 tahun 2010 tentang Pengadaan Barang/Jasa Pemerintah.
PMI. 2008. Guide to the Project Management Body of Knowledge(PMBOK® Guide). 4th ed. Newtown Square: Project Management Institute. 459 p.
Riduwan, 2006, Belajar Mudah Penelitian untuk Guru-Karyawan dan Peneliti Pemula, Alfabeta, Bandung.
Soeharto, Iman, 2001. Manajemen Proyek: Dari Konseptual Sampai Operasional, Jilid 2. Erlangga, Jakarta,
Surat Edaran Nomor: 40/se/dc/2016, Pedoman Umum Program Kota Tanpa Kumuh. Jakarta: Kementrian Pekerjaan Umum Direktorat Jendral Cipta Karya.
Wibowo, 2010, Intisari Kuliah Manajemen Resiko, Program Magister Teknik Sipil, Universitas Diponegoro, Semarang.

Downloads

Published

2022-05-21

How to Cite

Cahyono, L., Apriani, M., Trisna Nugraha, A., & Prasetyo Utomo, A. (2022). TIME RISK ANALYSIS OF IMPLEMENTATION SELF-MANAGED COMMUNITY PROJECT IN KALIANYAR - BANGIL VILLAGE . Jurnal Pensil : Pendidikan Teknik Sipil, 11(2), 142–151. https://doi.org/10.21009/jpensil.v11i2.25078

Most read articles by the same author(s)