IDENTIFICATION OF PRODUCTIVITY VALUES USING THE METHOD PRODUCTIVITY DELAY MODEL ON WALLER BEAM WORK

Authors

  • Melvin Yeremia Civil Engineering Department, Faculty of Engineering and Computer Science, Kristen Krida Wacana University
  • Ryobi Irfanto Civil Engineering Department, Faculty of Engineering and Computer Science, Kristen Krida Wacana University

DOI:

https://doi.org/10.21009/jpensil.v14i2.53988

Keywords:

Labor Productivity, Method Productivity Delay Model, Ideal Productivity

Abstract

Productivity can be interpreted as a comparison between physical output and real output with the actual input. This research aims to identify labor productivity on waller beam installation work in construction projects using the Method Productivity Delay Model (MPDM). The research method is carried out by conducting direct observations in the field and collecting productivity data using MPDM which is applied through delay analysis in the production cycle, techniques for evaluating work team balance and ensuring optimal labor allocation. The results showed that several factors, such as the environment contributing to the waller beam installation contributed 0.04, equipment factor contributed 0.21, labor factor contributed 0.36, material factor contributed 0.15, and management by 0.02 contributed to the delay and lower productivity. Ideal productivity was obtained at 1.737 units/s, overall productivity at 1.486 units/s, and % Achieved Productivity based on Ideal Productivity at 85.54%. In addition, the findings also emphasize the importance of proactive planning and real-time monitoring to reduce productivity losses and improve construction project performance.

References

Adebowale, O. J., & Agumba, J. N. (2023). A Meta-Analysis of Factors Affecting Construction Labour Productivity in the Middle East. Journal of Construction in Developing Countries, 28(1), 193–220. https://doi.org/10.21315/jcdc-12-21-0192

Bamayi, W. J., Kartika, N., & Robial, S. M. (2022). Productivity Analysis Of Floor Heroning Workers Using Work Sampling Method. Jurnal PenSil, 11(1), 162–170. https://doi.org/

10.21009/jpensil.v11i1.25294

Banobi, E. T., & Jung, W. (2019). Causes and mitigation strategies of delay in power construction projects: Gaps between owners and contractors in successful and unsuccessful projects. Sustainability (Switzerland), 11(21). https://doi.org/10.3390/

su11215973

Bigwanto, A., Widayati, N., Wibowo, M. A., & Sari, E. M. (2024). Lean Construction: A Sustainability Operation for Government Projects. Sustainability (Switzerland) , 16(8), 1–16. https://doi.org/10.3390/su16083386

Brown, R. (2020). Production Improvements in Offsite Construction Facilities Using Simulation and Lean Principles. https://era.library.ualberta.ca/items/9b2dc98f-a353-4fc1-9837-d01bc69264

56

Cahyono, L., Apriani, M., Nugraha, A. T., & Utomo, A. P. (2022). Time Risk Analysis Of Implementation Self-Managed Community Project In Bangil –Kalianyar Village. Jurnal PenSil, 11(1), 1–9. https://doi.org/10.21009/jpensil.v11i1.25294

Desfita, M., & Hamid, F. (2021). Work Sampling Methods Dalam Analisis Produktivitas Tenaga Kerja Kontruksi Proyek Pembangunan Gedung. Jurnal Teknologi Dan Sistem Informasi Bisnis, 3(1), 259–266. https://doi.org/10.47233/jteksis.v3i1.223

Dharmawan, H. I. (2020). Pekerjaan Pembesian Kolom (Analysis Of Labor Productivity In Steel Column Work). Tugas Akhir, 57.

Dharsono, M. S., & Hindun, S. (2024). Analysis Of Labor Productivity Of Beam And Floor Plate Work With Work Sampling Method. Jurnal Pensil, 13, 287–298. https://doi.org/10.21009/jpensil.v13i3.44934

Dwipurwanto, B. (2023). Analisis Produktivitas Tenaga Kerja Pemasangan Dinding Bata Ringan Dengan Metode Work Sampling Pada Pembangunan Rusun Surabaya. Inter Tech, 1(1), 22–27. https://doi.org/10.54732/i.v1i1.1021

Fauzi, R. R., Johari, G. J., Hantari, A. N., & Triguna, M. I. (2022). Identifikasi dan Penilaian Risiko pada Proyek Pembangunan Stasiun Garut Cibatu. Jurnal Konstruksi, 20(1), 51–61. https://doi.org/10.33364/konstruksi/v.20-1.1014

Gunawan, A., & Setyawan, A. (2022). Analisis Produktivitas Hasil Pekerjaan Konstruksi Antara Kerja Normal dan Kerja Lembur. Surakarta Civil Engineering Review, 49–61. http://ejurnal.unsa.ac.id/index.php/scer/article/view/12%0Ahttp://ejurnal.unsa.ac.id/index.php/scer/article/download/12/5

Gunawan, I., Istijono, B., & Boy, W. (2025). Analisis Faktor Penyebab Keterlambatan Pelaksanaan Proyek Sumber Daya Air (SDA) di Provinsi Kepulauan Riau. 12(1), 97–104. https://doi.org/10.21063/JTS.2025.V1201.097-104

Halpin, D. W., & Riggs, L. S. (1992). Planning And Analysis Of Construction Operations. John Wiley & Sons, Inc. https://books.google.co.id/books?id=ya-DeyVsxo8C&lpg=PP1&hl=

id&pg=PR3#v=onepage&q&f=false

Hanifah Eka Putri, N., Nyoman Dita Pahang Putra, I., & Rumintang Nauli, A. (2021). Perbandingan Dinding Precast dan Bata Ringan Terhadap Biaya dan Waktu pada Facade Proyek Suncity Apartment Sidoarjo. 7(1), 40–51.

Irawan, I., & Thesisa, C. (2024). Optimalisasi Produktivitas Keterlambatan MEP (Mechanichal Elektrikal Plumbing) Gedung F Poliklinik Terpadu RSUD Prof Dr Soekandar Mojosari Kabupaten Mojokerto Melalui Metode Earned Value. Basement : Jurnal Teknik Sipil, 2(2), 122–126. https://doi.org/10.36873/basement.v2i2.14831

Irfanto, R., Patty, E. M., & Lidyawati, R. (2024). Application of Value Engineering in Architectural Work on the Lahairoi Lateri Church, Ambon City. Jurnal PenSil, 13(2), 206–221. https://doi.org/10.21009/jpensil.v13i2.44019

Januardi, R., Nugroho, P. S., Mulyono, B., & Viqolbi, M. (2024). The effectiveness of construction operation performance measurement techniques and the challenges of application in preventing delays in construction projects. MATEC Web of Conferences, 402, 04002. https://doi.org/10.1051/matecconf/202440204002

Jefferson, W., & Andi, A. (2023). Analisis Produktivitas Pekerjaan Pasangan Bata Ringan Menggunakan Method Productivity Delay Model (Mpdm) Pada Proyek Apartemen Di Surabaya. Dimensi Utama Teknik Sipil, 10(1), 120–136. https://doi.org/10.9744/

duts.10.1.120-136

Kalyani, A., Dandin, S., & Kulkarni, D. M. (2021). Comparative Behaviour Of Retaining Wall With Strut And Ground Comparative Behaviour Of Retaining Wall With Strut And Ground Anchor Used In Underground Metro Station. July.

Kartika, N., Robial, S. M., & Pratama, A. (2021). Analisis Produktivitas Tenaga Kerja Pada Pekerjaan Kolom Di Proyek Pembangunan Gedung Pemda Kabupaten Sukabumi. Jurnal Momen Teknik Sipil, 3(2), 103. https://doi.org/10.35194/momen.v3i2.1207

Lakhani, B. G. (2024). The Role Of Prefabrication And Modular Construction In Reducing. October.

Lendra, L., Robby, R., & Faqih, N. (2023). Optimalisasi Sumber Daya Manusia Menggunakan Aplikasi Lips Pada Kegiatan Pendampingan Proyek Drainase Kota Palangka Raya. 10(2), 151–161.

Maharani, T., Nurtjahjaningtyas, I., & Wicaksono, L. A. (2022). Desain Ulang Dinding Penahan Tanah Menggunakan Dinding Diafragma dan Angkur pada Tanah Lunak (Studi Kasus: Grand Dharmahusada Lagoon). Jurnal Rekayasa Sipil Dan Lingkungan, 5(2), 142. https://doi.org/10.19184/jrsl.v5i2.19035

Malik, A. A., Dora, G., Derar, R., & Naeem, M. (2019). Diaphragm wall supported by ground anchors and inclined struts: A case study. International Journal of GEOMATE, 16(57), 150–156. https://doi.org/10.21660/2019.57.8170

Massie, M., Manoppo, F. J., & Dundu, A. K. T. (2022). Studi Penerapan Pengendalian Waktu, Biaya, Dan Mutu Pelaksanaan Proyek Boulevard Pantai Amurang Kabupaten Minahasa Selatan. Jurnal Ilmiah Media Engineering, 12(1), 2087–9334.

Michelle Susanto, M., & Jonathan Susilo, A. (2022). Perencanaan Sistem Penunjang Untuk Mengatasi Penambahan Deformasi Dinding Diafragma Pada Proyek Galian Basemen. JMTS: Jurnal Mitra Teknik Sipil, 5(4), 751–766. https://doi.org/10.24912/

jmts.v5i4.20292

Musarat, M. A., Khan, A. M., Alaloul, W. S., Blas, N., & Ayub, S. (2024). Automated monitoring innovations for efficient and safe construction practices. Results in Engineering, 22(March), 102057. https://doi.org/10.1016/j.rineng.2024.102057

Noor Syaima Mooniana, A., & Eliatun, E. (2024). Analisis Produktivitas Tenaga Kerja Pada Pekerjaan Pemasangan Dinding Bata Dengan Metode Work Sampling (Studi Kasus: Proyek Pembangunan Kantor Dinas Pengendalian Penduduk, Keluarga Berencana, Pemberdayaan Masyarakat, Perempuan Dan Perlindungan Anak (DP2KB. Jurnal Kacapuri : Jurnal Keilmuan Teknik Sipil, 7(1), 47. https://doi.org/10.31602/jk.v7i1.14695

Norjana, N., & Zulfiati, R. (2020). Analisa Produktivitas Tenaga Kerja terhadap Pekerjaan Kolom Dan Balok Beton Bertulang. Jurnal Talenta Sipil, 3(2), 82. https://doi.org/10.33087/talentasipil.v3i2.33

Prayoga Arfandi, B., & Abduh, M. (2021). Pengaruh Pandemi Covid-19 Terhadap Produktivitas Pekerjaan Konstruksi (Tinjauan Analisis Statistik Terhadap Penerapan Protokol Kesehatan). Seminar Keinsinyuran Program Studi Program Profesi Insinyur, 1(2), 374–380. https://doi.org/10.22219/skpsppi.v2i1.4311

Putri, A. N. (2021). Analisis Produktivitas Tenaga Kerja Terhadap Pekerjaan Keramik pada Masa Pandemi Covid-19 (Studi Kasus: Proyek Apartemen Jakarta Living Star). In Prosiding Seminar Nasional Teknik Sipil Politeknik Negeri Jakarta 2021 (Issue 25).

Putri Angelica, N., & Happy Puspasari, V. (2023). Faktor-Faktor Motivasi Kerja Tenaga Kerja Proyek Konstruksi di Kota Palangka Raya. Basement : Jurnal Teknik Sipil, 1(1), 11–16. https://doi.org/10.36873/basement.v1i1.8244

Putri, D. A., Muhtar, & Gunasti, A. (2021). Penerapan Metode CPM dan Crashing pada Proyek Gedung Training Center Universitas Jember. Jurnal Smart Teknologi, 2(2), 151–158.

Putri, K. N. R., Slamet, E., Saputri, Y. A., & Purnawan, M. Y. (2018). Pengamatan Produktivitas Pekerjaan Pengecoran Menggunakan Concrete Pump dengan Metode Time Studies Beserta Peningkatan Produktivitasnya, August, 1–17. https://doi.org/10.13140/RG.

2.2.17358.48965

Putu Raka Wibawa, S. (2020). Analisis Produktivitas Tenaga Kerja Pada Pengerjaan Pasangan Dinding Menggunakan Batu Bata Konvensional. Jurnal Ekonomi Volume 18, Nomor 1 Maret201, 2(1), 41–49.

Putujaya, M. C. (2020). Analisa Produktivitas Pekerjaan Kolom Dengan Metode Time Study Pada Proyek Pembangunan Ruang Kelas Mtsn 3 Pekanbaru.

Rocha, P. F., Ferreira, N. O., Pimenta, F., & Pereira, N. B. (2022). Impacts of Prefabrication in the Building Construction Industry. Encyclopedia, 3(1), 28–45. https://doi.org/10.3390

/encyclopedia3010003

Rompas, L. M. (2022). Analisis Proporsi Sumber Daya Pada Proyek Konstruksi (Studi Kasus Kota Manado ). Jurnal TEKNO, 20(82), 1189–1194.

Sangadji, F. A. (2023). Bimbingan Teknis Kompetensi Manajemen Proyek Untuk Kompetensi Tambahan Calon Lulusan Universitas Iqra Buru. ABDIKAN: Jurnal Pengabdian Masyarakat Bidang Sains Dan Teknologi, 2(1), 96–100. https://doi.org/10.55123/

abdikan.v2i1.1701

Santos Fonseca, S., Aguilera Benito, P., & Piña Ramírez, C. (2025). Development and Application of an Innovative Planning and Monitoring Tool to Optimize Construction Projects. Buildings, 15(2). https://doi.org/10.3390/buildings15020160

Sri Mulyati, A. (2024). Penahan Tanah Dengan Sheet Pile Dan Ground Anchor (Studi Kasus : Jalan Bukit Regency Gombel Golf Kota Semarang).

Tanne, Y. A., Pratama, A. P., & Rahardian, R. (2024). Analysis of Steel Beam Installation Operation Productivity (Case Study: Construction of University Pasundan Campus II). Media Komunikasi Teknik Sipil, 29(2), 233–242. https://doi.org/10.14710/mkts.

v29i2.54764

Tumilantouw, H. (2024). Penerapan Sistem Manajemen Konstruksi Pada Pekerjaan Kontruksi. 22(89).

Ulil Albab, A. (2021). Pelaksanaan Pekerjaan Struktur Bawah Gedung Parkir Kejaksaan Tinggi Lampung (Ahmad Ulil Albab) (Issue 1805081039).

Van Tam, N. (2024). Unveiling global research trends in construction productivity: a scientometric analysis of twenty-first century research. Smart Construction and Sustainable Cities, 2(1). https://doi.org/10.1007/s44268-024-00025-7

Wang, Y., Kumar Thangasamy, V., L. K. Tiong, R., & Limao, Z. (2022). A Review on Lean Construction for Construction Project Management. Journal of Construction Engineering and Management, 148(8), 43–60. https://doi.org/10.7764/RIC.00051.21

Wenas, V. T., Tjakra, J., & Sumanti, F. P. Y. (2023). Analisis Produktivitas Tenaga Kerja Pada Pekerjaan Pemasangan Rangka Atap Baja Menggunakan Metode MPDM (Method Productivity Delay Model). 21(85), 815–823.

Widjaja, O., & Makarim, C. A. (2020). Penggunaan Dinding Silang Pada Galian Dalam Di Tanah Sangat Lunak: Studi Kasus Proyek Apartemen DI Jalan Kebun Sirih Jakarta. Jurnal Muara Sains, Teknologi, Kedokteran Dan Ilmu Kesehatan, 4(2), 257. https://doi.org/10.24912/jmstkik.v4i2.7090

Wijaya, F. A. (2022). Analisis Produktivitas Tenaga Kerja Konstruksi Pada Pekerjaan Pemasangan Keramik Menggunakan MPDM (Method Productivity Delay Model). Tekno, 21(85).

Downloads

Published

2025-05-30

How to Cite

Yeremia, M., & Irfanto, R. (2025). IDENTIFICATION OF PRODUCTIVITY VALUES USING THE METHOD PRODUCTIVITY DELAY MODEL ON WALLER BEAM WORK. Jurnal Pensil : Pendidikan Teknik Sipil, 14(2), 343–355. https://doi.org/10.21009/jpensil.v14i2.53988