ANALYSIS OF THE INFLUENCE OF INTERNAL FACTORS ON PROJECT PERFORMANCE IN LOW-RISE COMMERCIAL BUILDING CONSTRUCTION PROJECTS IN TANGERANG
DOI:
https://doi.org/10.21009/jpensil.v13i2.44021Keywords:
Internal Factors, Time Performance, Cost Performance, SEM-PLSAbstract
From the construction statistics data of the city of Tangerang, in 2022 the construction business field contributes 8.16 percent to the total economy of the city of Tangerang, each construction project certainly has a certain work plan and work schedule, which is so that the project can be completed as planned. The impact that causes delays in project implementation time can be accompanied by increased costs of implementing the project. This study aims to know and identify and analyze factors - factors Labor factors, material factors, equipment factors, place characteristics factors, managerial factors, planning and scheduling factors and other factors. that affects time and cost performance. Research uses SEM-PLS to determine potentially influencing factors through literature review. The results of the study found that managerial factors had a significant influence on time performance with a coefficient value of 3.962, while planning and scheduling had a significant influence with a coefficient value of 2.773. While the effect of time performance on cost increase has a significant effect of 5.465.
References
Alaydrus, A. M., & Hardjomuljadi, S. (2018). Analisis Faktor Keterlambatan Dimulainya Pelaksanaan Proyek Konstruksi pada Model Kontrak Rancang Bangun. Jurnal Konstruksia, 10(1), 1–22. https://doi.org/10.24853/jk.10.1.95-116
Alsuliman, J. A. (2019). Causes of delay in Saudi public construction projects. Alexandria Engineering Journal, 58(2), 801–808. https://doi.org/10.1016/j.aej.2019.07.002
Andi, A., Susandi, S., & Wijaya, H. (2003). On Representing Factors Influencing Time Performance of Shop-House Constructions in Surabaya. Civil Engineering Dimension, 5(1), 7–13. https://doi.org/10.9744/ced.5.1.pp.%207-13
Ayu, E. S. (2017). Faktor penyebab peningkatan biaya material pada pelaksanaan pada proyek konstruksi di sumatra barat. Rekayasa, 07(02), 193–203.
Badan Pusat Statistik Kota Tangerang. (2023). Produk Domestik Regional Bruto Kota Tangerang Menurut Lapangan Usaha 2018-2022. https://tangerangkota.bps.go.id/publication/2023/04/05/8ee996bb2ec871709b5e6816/produk-domestik-regional-bruto-kota-tangerang-menurut-lapangan-usaha-2018-2022.html
Buya, M., Ashad, H., & Watono. (2022). Analisis Faktor Keterlambatan Waktu Pelaksanaan Konstruksi Pada Pembagunan Kantor Bupati Pulau Taliabu Dengan Metode Analytic Hierarchy Process. Jurnal Konstruksi, 01(01), 44–53.
Dapu, Y., Dundu, A., & Walangitan, R. (2016). Faktor – Faktor Yang Menyebabkan Cost Overrun Pada Proyek Konstruksi. Jurnal Sipil Statik, 4(10), 641–647.
Darmawan, M. B., & Yuwono, B. E. (2021). Faktor Keterlambatan Proyek Konstruksi Gedung Bertingkat pada Masa Pandemi. Prosiding Seminar Intelektual Muda, 2(2), 168–173. https://doi.org/10.25105/psia.v2i2.10330
Darmawi, D., Muttaqin, M., & Rauzana, A. (2020). Identifikasi Faktor-Faktor Utama Penyebab Terjadinya Keterlambatan Waktu Penyelesaian pada Pekerjaan Infrastruktur Gedung di Banda Aceh. Jurnal Arsip Rekayasa Sipil Dan Perencanaan, 3(1), 70–79. https://doi.org/10.24815/jarsp.v3i1.16456
Dwinanda, N., Eka Priana, S., & Herista, F. (2023). Analisis Faktor-Faktor Penyebab Keterlambatan Pelaksanaan Pekerjaan Proyek Konstruksi Tahun 2021 di Kabupaten Lima Puluh Kota. Ensiklopedia Research and Community Service Review, 2(2), 175–180. https://doi.org/10.33559/err.v2i2.1715
Endawati, E. (2022). Evaluasi faktor perubahan desain, ketersediaan material dan produktivitas tenaga kerja terhadap biaya pada proyek bangunan perkantoran. Universitas Mercu Buana.
Endawati, E., & Susetyo, B. (2023). Evaluation of Factors of Design Change, Material Availability and Labor Productivity Against Cost Performance on Office Building Projects. Journal of Social Research, 2(5), 1691–1707. https://doi.org/10.55324/josr.v2i5.875
Hair, Black, W. C., Babin, B. J., Anderson, R. E., Black, W. C., & Anderson, R. E. (2018). Multivariate Data Analysis. In Wiley Series in Probability and Statistics (pp. 95–120). https://doi.org/10.1002/9781119409137.ch4
Halim, E. C., Andi, A., & Rahardjo, J. (2021). Aplikasi Interpretive Structural Modeling (ISM) pada Faktor-Faktor Penyebab Keterlambatan Proyek Kontruksi di Surabaya. Dimensi Utama Teknik Sipil, 8(1), 60–77. https://doi.org/10.9744/duts.8.1.60-77
Indrayana, D. V. (2020). Evaluasi Integrasi Standar Keamanan, Keselamatan, Kesehatan, Dan Keberlanjutan (K4) Dengan Sistem Manajemen Keselamatan Dan Kesehatan Kerja (Smk3) Pada Kinerja Proyek Infrastruktur Jalan. Universitas Mercu Buana.
Irian, R. T. K., Sembayang, M., & Yogi, M. R. A. (2022). Analisis Faktor Dominan Penyebab Terjadinya Pembengkakan Biaya (Cost Overrun) pada Proyek Konstruksi Gedung Pemerintah Kategori Kecil di Kota Pekanbaru. Jurnal Teknologi Dan Rekayasa Sipil, 1(1), 37–43. https://doi.org/10.56208/jtrs.v1.i1-hal37-43
Iskandar, Y., Susetyo, B., & Suroso, A. (2022). Pengaruh Contract Change Order (CCO) terhadap Kinerja Biaya pada Proyek Hunian Bertingkat Tinggi. Jurnal Konstruksia |, 13(2), 55–64.
Kurniawan, H., & Anggraeni, I. A. A. (2020). Analisis Risiko Rantai Pasok Material Terhadap Keterlambatan Pelaksanaan Proyek Konstruksi. Rekayasa Sipil, 14(1), 43–50. https://doi.org/10.21776/ub.rekayasasipil.2020.014.01.6
Listanto, N., & Hardjomuljadi, S. (2018). Analisis faktor penyebab keterlambatan pembayaran kontraktor kepada subkontraktor pada proyek gedung bertingkat. Jurnal Konstruksia, 10(1), 59–72. https://doi.org/10.24853/jk.10.1.59-72
Ma’rifah, L. (2023). Analisis Pengaruh Waste Material Dan Management Material Pada Proyek Rusunawa Dengan Lean Construction Untuk Meningkatkan Kinerja Biaya Proyek. Universitas Mercu Buana.
Melyana, T. S., & Sulistio, H. (2022). Kinerja Pekerja Konstruksi Yang Dipengaruhi Kemampuan, Motivasi Dan Disiplin Kerja di Jabodetabek. JMTS: Jurnal Mitra Teknik Sipil, 5(3), 36–44.
Mustafaruddin, M., Afifuddin, M., & Munir, A. (2018). Faktor-Faktor Penghambar Pembangunan Rumah Layak Huni untuk Kaum Dhuafa di Provinsi Aceh (Study Kasus: Kabupaten Aceh Utara). Jurnal Arsip Rekayasa Sipil Dan Perencanaan, 1(4), 119–129. https://doi.org/10.24815/jarsp.v1i4.12462
Paparang, T., Walangitan, D. R. O., & Pratasis, P. A. K. (2018). Identifikasi Faktor Penyebab Cost Overruni Biaya Pada Proyek Terminal Antar-Kabupaten-Provinsi Tangkoko Bitung. Jurnal Sipil Statik, 6(10), 813–822.
Perdana Putra, I. K. B. W., Parami Dewi, A. A. D., & Sudarsana, D. K. (2021). Evaluasi Risiko Proyek Pembangunan Gedung RSIA Puri Bunda Tabanan-Bali. JURNAL SPEKTRAN, 9(2), 124. https://doi.org/10.24843/SPEKTRAN.2021.v09.i02.p04
Proboyo, B. (1999). Keterlambatan waktu pelaksanaan proyek klasifikasi dan peringkat dari penyebab-penyebabnya. Civil Engineering Dimension, 1(1), 46–58. https://doi.org/https://doi.org/10.9744/ced.1.1.pp.%2046-58
Putra, D. M. (2022). Penyebab Keterlambatan Dalam Pelaksanaan Gedung Sekolah Bertingkat Di Serang. Jurnal Deformasi, 7(2), 204. https://doi.org/10.31851/deformasi.v7i2.9056
Putra, J. C. P., Safrilah, S., & Asmi, A. (2017). Aplikasi Structural Equation Modeling Dalam Analisis Faktor-Faktor Penyebab Keterlambatan. Rekayasa Sipil, 6(2), 113–122.
Rachid, Z., Toufik, B., & Mohammed, B. (2019). Causes of schedule delays in construction projects in Algeria. International Journal of Construction Management, 19(5), 371–381. https://doi.org/10.1080/15623599.2018.1435234
Rachmat, A., Kadir, Y., & Ependi, R. (2021). Konstruksi Terhadap Waktu Pelaksanaan (Studi Kasus Pada Proyek Pembangunan Rumah Susun Tinggi Polri Pesing Jakarta Barat). Techno-Socio Ekonomika, 14(1), 70–86. https://doi.org/10.32897/techno.2021.14.1.582
Rahmad, S. H., & Suhardi, M. A. (2019). Struktural Equation Modeling (SEM) konsep dasar dan aplikasi program Smart PLS 3.2.8 dalam riset bisnis. PT Inkubator Penulis Indonesia.
Rani, H. A. (2023). Manajemen Proyek Konstruksi. Yayasan Kita Menulis.
Remi, F. F. (2017). Kajian Faktur Penyebab Cost Overrun pada Proyek Konstruksi Gedung. Jurnal Teknik Mesin, 6(2), 33. https://doi.org/10.22441/jtm.v6i2.1187
Robi, M., Kusnandar, D., & Sulistianingsih, E. (2017). Penerapan Structural Equation Modeling (SEM). Buletin Ilmiah Mathematika, Statistik Dan Terapannya, 6(2), 113–120.
Rofi Henindia, & Suroso, A. (2022). Analysis of the Factors Causing Delay in Pile Foundation Work for Medium-Story Building Project. Journal of Applied Science, Engineering, Technology, and Education, 4(1), 27–38. https://doi.org/10.35877/454RI.asci850
Rosdianto, M. A., Suef, M., & Angreni, E. (2018). Analisis Peristiwa Penyebab pada Keterlambatan Proyek Apartemen. Accounting and Management Journal, 2(1), 29–38.
Ruslim, S. N., Hermawan, C. T., & Limanto, S. (2023). Analisis Penyebab, Dampak, dan Antisipasinya terhadap Keterlambatan Proyek Konstruksi di Surabaya. Jurnal Dimensi Pratama Teknik Sipil, 12(1), 71–78.
Simanjuntak, M. R. A., & Dalian, T. (2020). Analisis Faktor dan Variabel Proses Konstruksi (Studi Kasus Proyek Bangunan Gedung Apartemen XYZ). SNITT Poltekba, 4, 560–564.
Sun, Y., Wang, J., Wu, J., Shi, W., Ji, D., Wang, X., & Zhao, X. (2020). Constraints Hindering the Development of High-Rise Modular Buildings. Applied Sciences, 10(20), 7159. https://doi.org/10.3390/app10207159
Sutarja, I. N., Jaya, N. M., & Sukoyo, A. P. (2020). Analisis Faktor Penyebab Keterlambatan Penyelesaian Proyek Hotel Di Kabupaten Badung dan Kota Denpasar. Jurnal Spektran, 8(2), 160–168.
Wuala, H. D., & Rarasati, A. D. (2020). Causes of delays in construction project for developing Southeast Asia countries. IOP Conference Series: Materials Science and Engineering, 830(2), 022054. https://doi.org/10.1088/1757-899X/830/2/022054