COMPARATIVE ANALYSIS OF PLASTERING WORK EXECUTION TIME ON LABOUR PRODUCTIVITY WITH WORK SAMPLING METHOD
DOI:
https://doi.org/10.21009/jpensil.v14i2.54314Keywords:
Productivity, Work sampling, Labor Utilization Rate, plasteringAbstract
Labor productivity is the main parameter in the success of a construction job. This study aims to analyze the level of productivity and the level of Labor Utilization Rate (LUR) in plastering work using the work sampling method, and the most effective time correlation between morning and afternoon. This research was conducted by direct observation for 3 days. The results showed that the highest productivity value was 14.30 m²/hour in the afternoon, and the lowest productivity value was 6.86 m²/hour in the morning. The Labor Utilization Rate (LUR) values in the morning and afternoon were 57.9% and 65.9%, indicating that the afternoon time was more effective than the morning time. However, there was a significant difference in productivity between morning and afternoon time overall, and it can still be categorized as effective with a Labor Utilization Rate (LUR) value of 61.9%, which exceeds 50%.
References
Adistana, G. A. Y. P., HS, M. S., Mahardi, P., & Sofianto, M. F. (2022). Assessment of E-Procurement Subjects’ Missteps for Construction and Consultancy Services Throughout the Surabaya City Area As an Educational Adjunct for Project Tender Courses. Jurnal PenSil, 11(1), 1–9. https://doi.org/10.21009/jpensil.v11i1.25294
Aghazadeh, E., Yildirim, H., & Aliparast, S. (2019). Materials Selection in The Construction Projects: Challenges, Criteria & Patterns. International Journal of Advances in Mechanical and Civil Engineering, 6, 2394–2827. http://iraj.in
Andi Andi, koento danny wibowo, & Andri Prasetya. (2004). Analisa Produktifitas Pekerja Dengan Metode Work Sampling Studi Kasus Pada Proyek X Dan Y. Civil Engineering Dimension, 6(2), pp.72-79. http://puslit2.petra.ac.id/ejournal/index.php/civ/article/ view/16114
Anditiaman, N. M., Latief, R. U., Rahim, I. R., & Arifuddin, R. (2020). Identification of construction productivity components in Indonesia. Case study of construction projects at the ministry of public works and housing provision (PUPR). IOP Conference Series: Earth and Environmental Science, 419(1). https://doi.org/10.1088/1755-1315/ 419/1/012146
Arsitektur, J., Nusa, U., & Indonesia, N. (2024). Analisa Produktivitas Tenaga Kerja Di Lapangan Pekerjaan Dinding Pada Proyek Pembangunan Penambahan Ruang Kelas Baru Analysis of Labor Productivity in the Wall Work Site on the New Classroom Addition Construction Project. 72–78.
Ashad, H. H., & Musa, R. (2020). PROYEK PEMBANGUNAN EMBUNG DAN JARINGAN. 4(1), 49–58.
Asher Prasetyo, D., Pintardi Chandra, H., & Soehendro, R. (2017). Analisi Produktivitas Tenaga Kerja Dengan Metode Work Sampling: Studi Kasus Proyek Tunjangan Plaza 6. 1–8.
Azzam, A., Miranda, S., & Indrawati, S. (2019). Information system design using labor productivity measurement for construction. IOP Conference Series: Materials Science and Engineering, 528(1). https://doi.org/10.1088/1757-899X/528/1/012003
Baharin, R., Syah Aji, R. H., Yussof, I., & Saukani, N. M. (2020). Impact of human resource investment on labor productivity in Indonesia. Iranian Journal of Management Studies, 13(1), 139–164. https://doi.org/10.22059/IJMS.2019.280284.673616
Boughaba, A., & Bouabaz, M. (2020). Identification and risk management related to construction projects. Advances in Computational Design, 5(4), 445–465. https://doi.org/ 10.12989/acd.2020.5.4.445
Boulkenafet, N., Boudjellal, K., & Bouabaz, M. (2023). Optimization of productivity in the rehabilitation of building linked to BIM. Advances in Computational Design, 8(2), 179–190.
Buraida. (2012). Kajian Efektivitas Kegiatan Tenaga Kerja Proyek Konstruksi berdasarkan Nilai Labor Utilization Rate (LUR). Jurnal Teknik Sipil, 1(3), 227–238.
Dharsono, M. S., & Hindun, S. (2024). at: http://journal.unj.ac.id. 13, 287–298. https://doi.org /10.21009/jpensil.v13i3.44934
Diniaty, D. (2015). Analisis Beban Kerja dengan Menggunakan Metode Work Sampling. Jurnal Teknik Industri: Jurnal Hasil Penelitian Dan Karya Ilmiah Dalam Bidang Teknik Industri, 1(2), 60–69.
Durdyev, S., Ismail, S., & Kandymov, N. (2018). Structural Equation Model of the Factors Affecting Construction Labor Productivity. Journal of Construction Engineering and Management, 144(4). https://doi.org/10.1061/(asce)co.1943-7862.0001452
Edum-Fotwe, F. T. (1999). Construction Productivity Management. In Engineering Construction and Architectural Management (Vol. 6, Issue 4). Longman, 1998. https://doi.org/ 10.1046/j.1365-232x.1999.00125.x
El-Gohary, K. M., & Aziz, R. F. (2014). Factors Influencing Construction Labor Productivity in Egypt. Journal of Management in Engineering, 30(1), 1–9. https://doi.org/10.1061/ (asce)me.1943-5479.0000168
Elizar, Harmiyati, Santoso, R. A., & Irawan, M. N. (2020). Analisis Produktivitas Pekerja Dengan Konsep Value Stream Mapping Pada Pekerjaan Kolom dan Balok. Jurnal Teknik Sipil Dan Teknologi Konstruksi, 6(1), 31–40. http://jurnal.utu.ac.id/jtsipil/article /view/1955%0Ahttp://jurnal.utu.ac.id/jtsipil/article/viewFile/1955/1422
Enshassi, A., Mohamed, S., Mustafa, Z. A., & Mayer, P. E. (2007). Journal of Civil Engineering and Management Factors Affecting Labour Productivity in Building Projects in the Gaza Strip. Journal of Civil Engineering and Management, XIII(4), 245–254. http:/www. jcem.vgtu.lt
Ferdatama Gama Bagaskara, & Budi Priyanto. (2023). Analisis Produktivitas Tenaga Kerja Pada Pekerjaan Plesteran Dinding Proyek Masjid Mibas. Journal of Civil Engineering Building and Transportation, 7(1), 212–217. https://doi.org/10.31289/jcebt.v7i1.9083
Firman kresna, B. S., & Dewita H. (2016). Produktivitas Pekerja Bekisting Dan Pembesian Dengan Menggunakan Metode Work Sampling Pada Proyek Gedung. Jurnal Sains Dan Teknologi Utama, XI.
Hwang, B.-G., Zhu, L., & Ming, J. T. T. (2017). Factors Affecting Productivity in Green Building Construction Projects: The Case of Singapore. Journal of Management in Engineering, 33(3), 1–12. https://doi.org/10.1061/(asce)me.1943-5479.0000499
Jarkas, A. M. (2010). Analysis and measurement of buildability factors affecting edge formwork labour productivity. Journal of Engineering Science and Technology Review, 3(1), 142–150. https://doi.org/10.25103/jestr.031.24
Jarkas, A. M., Balushi, R. A. Al, Raveendranath, P. K., Jarkas, A. M., Balushi, R. A. Al, & Faktor, P. K. R. (2016). Faktor penentu produktivitas tenaga kerja konstruksi. 3599.
Joshi, P., Tribhuvansantosh, U., & Shrestha, K. (2019). Analisis Produktivitas Tenaga Kerja Selama Operasi Pembetonan pada Konstruksi Bangunan Lembah Kathmandu.
Kevin, J., Gordon Thiery, & Alifen, R. S. (2019). Analisis Labor Utilization Rate Pada Jam Kerja Normal Dan Jam Kerja Lembur. Jurnal Dimensi Pratama …, 144–151. http://publication.petra.ac.id/index.php/teknik-sipil/article/view/9611
Lawaju, N., Parajuli, N., & Shrestha, S. K. (2021). Analysis of Labor Productivity of Brick Masonry Work in Building Construction in Kathmandu Valley. Journal of Advanced College of Engineering and Management, 6, 159–175. https://doi.org/10.3126/jacem.v6i0. 38356
Liou, B. F. (1986). Work sampling can predictunit rate productivity. 112(1), 90–103.
Montaser, N. M., Mahdi, I. M., Mahdi, H. A., & Rashid, I. A. (2018). Factors Affecting Construction Labor Productivity for Construction of Pre-Stressed Concrete Bridges. International Journal of Construction Engineering and Management, 7(6), 193–206. https://doi.org/10.5923/j.ijcem.20180706.01
Muchdarsyah, S. (2003). Produktivitas Apa dan Bagaimana. Bumi Aksara.
Muslim, I., Z, Z., & Lubis, F. (2019). Analisis Produktivitas Tenaga Kerja Pada Pekerjaan Dinding Facade (Studi Kasus Pada Proyek Pembangunan Hotel Pop Pekanbaru). SIKLUS: Jurnal Teknik Sipil, 5(1), 12–22. https://doi.org/10.31849/siklus.v5i1.2388
Oglesby et al., 1989. (1989). Productivity Improvement In Construction. McGraw-Hill Series In Construction Engineering and Project Management.
Oktavio, K., Dharmawan, R. K., & Nugraha, P. (2020). Survey Mengenai Faktor-Faktor Yang Memengaruhi Produktivitas Pekerja Pada Beberapa Proyek Konstruksi Di Surabaya. Jurnal Dimensi Pratama Teknik Sipil, 9(1), 141–148.
Pascoal, E., Harimurti, & Unas El, S. (2017). Analisis Produktivitas Jumlah Tenaga Kerja Pada Pekerjaan Plesteran Dindin Dengan Metode Work Study. Jurnal Mahasiswa Jurusan Teknik Sipil, 2.
Rivas, R. A., Borcherding, J. D., González, V., & Alarcón, L. F. (2011). Analysis of Factors Influencing Productivity Using Craftsmen Questionnaires: Case Study in a Chilean Construction Company. Journal of Construction Engineering and Management, 137(4), 312–320. https://doi.org/10.1061/(asce)co.1943-7862.0000274
Shehata, M. E., & El-Gohary, K. M. (2011). Towards improving construction labor productivity and projects’ performance. Alexandria Engineering Journal, 50(4), 321–330. https://doi.org/10.1016/j.aej.2012.02.001
Suharto, I. P., & Sulistio, H. (2020). Produktivitas Pekerja Dalam Pekerjaan Plesteran Dinding Bata Dengan Metode Crew Balance Chart. JMTS: Jurnal Mitra Teknik Sipil, 3(4), 1373. https://doi.org/10.24912/jmts.v3i4.8378
Taufan, M. (2018). Penentuan Jumlah Tenaga Kerja yang Optimal dengan Metode Work Sampling Di IKM Griya Mank Gudo Jombang. Jurnal Valtech, 01(01), 31–35.
Thomas, H. R., Horman, M. J., de Souza, U. E. L., & Zavřski, I. (2002). Reducing Variability to Improve Performance as a Lean Construction Principle. Journal of Construction Engineering and Management, 128(2), 144–154. https://doi.org/10.1061/(asce)0733-9364(2002)128:2(144)
Thomas, A. V., & Sudhakumar, J. (2013). Critical analysis of the key factors affecting construction labour productivity-an Indian perspective. International Journal of Construction Management, 13(4), 103–125. https://doi.org/10.1080/15623599.2013.108 78231
Widnyana, I. N. S., & Mahendra, I. P. A. A. (2023). Analisis Produktivitas Tenaga Kerja Pada Pekerjaan Plat Lantai Dengan Metode Work Sampling. Widya Teknik, 19(1), 29–34. https://doi.org/10.32795/widyateknik.v19i1.4478
Yanti, G. (2017). Produktivitas Tenaga Kerja Dengan Metode Work Sampling Proyek Perumahan Di Kota Pekanbaru. SIKLUS: Jurnal Teknik Sipil, 3(2), 100–106. https://doi.org/10.31849/siklus.v3i2.385
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2025 Dwi Dzulma Susanti, Fepy Supriani, Rena Misliniyati, Lindung Zalbuin Mase, Hardiansyah

This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.







.png)
.png)
1.png)