Analysis of Lead Time Reduction in Pre-Delivery Installation Process of Excavator Units at PT. XYZ Assembly Plant

Penulis

  • Dibyo Setiawan Politeknik Negeri Bandung
  • Tubagus Syah Fatahillah Gelagah Wangi Bintaran Politeknik Negeri Bandung
  • Apri Setiawan Politeknik Negeri Bandung
  • Hanni Maksum Ardi Politeknik Negeri Bandung
  • Herbert Hasudungan Siahaan Universitas Mpu Tantular
  • Cahyo Wibowo Universitas Mpu Tantular

DOI:

https://doi.org/10.21009/JKEM.11.1.5

Kata Kunci:

heavy equipment, productivity, pie chart, pareto diagram, fishbone diagram

Abstrak

The Pre-Delivery Installation (PDI) Department of PT. XYZ is tasked with carrying out the installation process of imported heavy equipment attachment units, including one of the leading excavator units. Obstacles that arise can affect installation productivity. The gap between the actual installation results of 78 units and the company's target of 156 units requires a solution or resolution to improve the process that can be implemented. Therefore, it is necessary to investigate the wait time associated with decreased productivity, which is the longest component of the installation process. This work has a purpose to analyze lead time of the excavator attachment unit installation process. The method is applied with a time study approach referring to data sheets and observations, then processing lead time data using pie charts, Pareto diagrams, and fishbone diagrams. Furthermore, we review the planning calendar, realization, and improvement engineering. Reduction is carried out by providing additional work personnel and procuring sanding machine tools to reduce the installation and critical time of the planning calendar. The realization condition for 562 minutes with the implementation of improvement engineering is reduced to 318 minutes. Thus, it can speed up implementation time of the excavator attachment in unit installation process to 224 minutes or 44%.

Referensi

[1] A. U. Khan, L., Huang, E. Onstein, and Y. Liu, "Overview of emerging technologies for improving the performance of heavy-duty construction machines," IEEE Access, vol. 10, pp. 103315-103336, 2022, doi: 10.1109/ACCESS.2022.3209818.

[2] C. Cunanan, M. K. Tran, Y. Lee, S. Kwok, V. Leung, and M. Fowler, "A review of heavy-duty vehicle powertrain technologies: diesel engine vehicles, battery electric vehicles, and hydrogen fuel cell electric vehicles," Clean Technologies, vol. 3, no. 2, pp. 474-489, 2021, doi: 10.3390/cleantechnol3020028.

[3] Y. Chen, D. Huang, Z. Liu, M. Osmani, and P. Demian, "Construction 4.0, industry 4.0, and building information modeling (BIM) for sustainable building development within the smart city," Sustainability, vol. 14, no. 16, p. 10028, 2022, doi: 10.3390/su141610028.

[4] A. R. Sugiarto, D. P. Purnama, and M. M. A. Saripudin, “Perkembangan teknologi alat berat di era konstruksi 4.0,” Jurnal Forum Mekanika, vol. 12, no. 1, pp. 28–36, 2023, doi: 10.33322/forummekanika.v12i1.2023

[5] A. P. Sinurat, M. P. N. Saing, and P. F. X. Nahampun, “Pengaruh pola pemuatan excavator komatsu PC 2000 terhadap produktivitas overburden removal pada PT. x,” Jurnal Ilmiah Kajian Multidisipliner, vol. 8, no. 12, pp. 72–78, 2024.

[6] F. F. Fauzi and H. Dani, “Analisa perbandingan produktivitas alat berat dum truck tipe a , b dan c pada proyek konstruksi,” Jurnal Rekayasa Teknik Sipil, vol. 9, no. 2, pp. 1–7, 2021.

[7] S. G. Gebeyehu, M. Abebe, and A. Gochel, “Production lead time improvement through lean manufacturing,” Cogent Engineering, vol. 9, no. 1, p. 2034255, 2022, doi: 10.1080/23311916.2022.2034255.

[8] P. M. Masuti and U. A. Dabade, “Lean manufacturing implementation using value stream mapping at excavator manufacturing company,” Materials Today: Proceedings, vol. 19, no. 2, pp. 606–610, 2019, doi: 10.1016/j.matpr.2019.07.740.

[9] M. A. Samad, J. Abdullah, and M. A. H. Rifat, “Reduction of manufacturing lead time by value stream mapping of a selected RMG factory in bangladesh,” Asian Journal of Engineering and Applied Technology, vol. 12, no. 1, pp. 10–17, 2023, doi: 10.51983/ajeat-2023.12.1.3578.

[10] J. Singh and H. Singh, “Application of lean manufacturing in automotive manufacturing unit,” International Journal of Lean Six Sigma, vol. 11, no. 1, pp. 171–210, 2020, doi: 10.1108/IJLSS-06-2018-0060.

[11] H. R. Zadry, L. Susanti, B. Yuliandra, and D. Jumento, Analisis Dan Perancangan Sistem Kerja, 1st ed., Padang City: Andalas University Press, 2011.

[12] N. Maliha, N. Latianingsih, and A. Azwar, “Implementasi program corporate social responsibility (CSR) Yayasan komatsu indonesia peduli dalam mewujudkan citra positif perusahaan PT Komatsu indonesia,” Jurnal Administrasi Profesional, vol. 1, no. 1, pp. 22–29, 2022, doi: 10.32722/jap.v1i01.5076.

[13] M. H. A. A. Tanjung, N. B. Harahap, M. E. Siboro, and M. Harahap, “Program magang keahlian sebagai sarana praktik dan peningkatan kompetensi mahasiswa di bidang penerbitan,” Indonesian Journal of Community Services, vol. 5, no. 1, pp. 1-11, 2023, doi: 10.30659/ijocs.5.1.1-11.

[14] M. S. Isyanto, Sugiyanto, I. Bahiuddin, A. A. Ismail, A. Khaerudin, and I. Muslih, “Pembuatan trepos (travel protection system) sebagai upaya penurunan travel dispatch pada small excavator,” Jurnal Teknologi dan Rekayasa Alat Berat, vol. 2, no. 1, pp. 8–16, 2025, doi: 10.22146/jtrab.v2i1.13665.

[15] K. Nadiyah and G. S. Dewi, "Quality control analysis using flowchart, check sheet, p-chart, pareto diagram and fishbone diagram," Jurnal OPSI, vol. 15, no. 2, pp. 183-188, 2022, doi: 10.31315/opsi.v15i2.7445.

[16] N. Trivedi and B. K. Mawandiya “Application of fishbone diagram & pareto analysis for improving quality and reliability of MCCB – a case study”, Journal of Engineering and Technology, vol. 2, no. 2, pp. 27–32, 2025.

[17] M. Sydor, R. Mirski, K. Stuper-Szablewska, and T. Rogoziński, “Efficiency of machine sanding of wood,” Applied sciences, vol. 11, no. 6, p. 2860, 2021, doi: 10.3390/app11062860.

[18] J. Matuszak, K. Zaleski, K. Ciecieląg, and A. Skoczylas, “Analysis of the effectiveness of removing surface defects by brushing,” Materials, vol. 15, no. 21, p. 7833, 2022, doi: 10.3390/ma15217833.

[19] M. B. M. Bakhit and A. A. M Yusof, “Mini sander machine for small-volume production,”Journal of Engineering and Technology, vol. 15, no. 2, pp. 83-96, 2024, doi: 10.54554/jet.2024.15.2.005.

[20] A. Hakim, “The influence of duties and education experience on new personnel duties in the indonesian national army's operating staff environment’” International Journal of Social Science and Business, vol. 7, no. 1, pp. 199-207, 2023, doi: 10.23887/ijssb.v7i1.57654.

Diterbitkan

2026-01-31

Cara Mengutip

[1]
Dibyo Setiawan, T. S. F. G. W. Bintaran, A. Setiawan, H. M. Ardi, H. H. Siahaan, dan C. Wibowo, “Analysis of Lead Time Reduction in Pre-Delivery Installation Process of Excavator Units at PT. XYZ Assembly Plant”, J. Konv. Ener. Manuf. , vol. 11, no. 1, hlm. 37 – 52, Jan 2026.

Terbitan

Bagian

Articles